Which step is NOT part of the project close-out process?

Conducting a punch list

Responding to owner’s questions during the shakedown period

Verifying correction of punch list items

The project close-out process is crucial to ensuring that all aspects of a project are completed satisfactorily before it is officially considered finished. Typically, it encompasses several key steps aimed at addressing any remaining issues and confirming that the project meets all specified requirements.

Conducting a punch list is an essential part of this process, where a list of incomplete or unsatisfactory items is created to ensure everything is addressed before final acceptance. Responding to the owner's questions during the shakedown period also forms part of the close-out, allowing the client to become familiar with the project and providing an opportunity for any last-minute inquiries or concerns. Finalizing warranty documents involves organizing and handing over all warranties related to the materials and systems used in the project, ensuring the owner understands their protections moving forward.

Verifying the correction of punch list items is, in fact, a crucial step in the close-out process, as it ensures that all items listed as incomplete or requiring attention have been properly addressed. Therefore, the answer indicating that verifying the correction of punch list items is NOT part of the project close-out process does not align with standard practices in project management and interior design.

Get further explanation with Examzify DeepDiveBeta

Finalizing warranty documents